Prioritizes the rapid development of AI data centers by easing federal regulatory burdens and using federally owned resources. Defines “Data Center Project” as facilities requiring more than 100 MW of AI-related load and establishes “Covered Components,” “Covered Component Projects,” and “Qualifying Projects” based on capital investment (≥$500 million), electric load thresholds, national security relevance, or agency designation. Directs the Secretary of Commerce to launch a financial support initiative for Qualifying Projects, including loans, loan guarantees, grants and tax incentives. Requires agencies to identify categorical exclusions under National Environmental Policy Act (NEPA) and limits when federal financial assistance constitutes a “major Federal action” to expedite environmental review. Authorizes the Federal Permitting Improvement Steering Council (FPISC) to designate Qualifying Projects for inclusion on the Permitting Dashboard under FAST-41 for expedited review and transparency. Directs the Environmental Protection Agency to streamline permitting under the Clean Air Act, Clean Water Act, and other laws, and to identify Brownfield and Superfund Sites for reuse by Qualifying Projects. Requires programmatic consultation under the Endangered Species Act and directs review of nationwide permits under the Clean Water Act and Rivers and Harbors Act to determine whether activity-specific permits are needed. Directs the Departments of the Interior and Energy to provide authorizations for federal lands and directs the Secretary of Defense to identify and competitively lease suitable military lands for infrastructure supporting Qualifying Projects. Revokes Executive Order 14141.
Paper
Full text
Executive Order on Accelerating Federal Permitting of Data Center Infrastructure
ETO AGORA · U.S. regulations, executive orders, and agency policies · 2025
Summary
Prioritizes the rapid development of AI data centers by easing federal regulatory burdens and using federally owned resources.
Defines “Data Center Project” as facilities requiring more than 100 MW of AI-related load and establishes “Covered Components,” “Covered Component Projects,” and “Qualifying Projects” based on capital investment (≥$500 million), electric load thresholds, national security relevance, or agency designation.
Directs the Secretary of Commerce to launch a financial support initiative for Qualifying Projects, including loans, loan guarantees, grants and tax incentives.
Requires agencies to identify categorical exclusions under National Environmental Policy Act (NEPA) and limits when federal financial assistance constitutes a “major Federal action” to expedite environmental review.
Authorizes the Federal Permitting Improvement Steering Council (FPISC) to designate Qualifying Projects for inclusion on the Permitting Dashboard under FAST-41 for expedited review and transparency.
Directs the Environmental Protection Agency to streamline permitting under the Clean Air Act, Clean Water Act, and other laws, and to identify Brownfield and Superfund Sites for reuse by Qualifying Projects.
Requires programmatic consultation under the Endangered Species Act and directs review of nationwide permits under the Clean Water Act and Rivers and Harbors Act to determine whether activity-specific permits are needed.
Directs the Departments of the Interior and Energy to provide authorizations for federal lands and directs the Secretary of Defense to identify and competitively lease suitable military lands for infrastructure supporting Qualifying Projects.
Revokes Executive Order 14141.
Directs federal support for rapid buildout of AI data center infrastructure, including regulatory easing and use of federally owned land.
By the authority vested in me as President by the Constitution and the laws of the United States of America, it is hereby ordered:
Section 1. Policy and Purpose. My Administration has inaugurated a golden age for American manufacturing and technological dominance. We will pursue bold, large-scale industrial plans to vault the United States further into the lead on critical manufacturing processes and technologies that are essential to national security, economic prosperity, and scientific leadership. These plans include artificial intelligence (AI) data centers and infrastructure that powers them, including high‑voltage transmission lines and other equipment. It will be a priority of my Administration to facilitate the rapid and efficient buildout of this infrastructure by easing Federal regulatory burdens.
In addition, my Administration will utilize federally owned land and resources for the expeditious and orderly development of data centers. This usage will be done in a manner consistent with the land’s intended purpose — to be used in service of the prosperity and security of the American people.
Defines "Data Center Project" as a facility with >100 megawatt load for Artificial Intelligence, and "Covered Components" as its required infrastructure including energy infrastructure, semiconductors, and data storage products.
Sec. 2. Definitions. For purposes of this order:
(a) “Data Center Project” means a facility that requires greater than 100 megawatts (MW) of new load dedicated to AI inference, training, simulation, or synthetic data generation.
(b) “Covered Components” means materials, products, and infrastructure that are required to build Data Center Projects or otherwise upon which Data Center Projects depend, including:
(i) energy infrastructure, such as transmission lines, natural gas pipelines or laterals, substations, switchyards, transformers, switchgear, and system protective facilities;
(ii) natural gas turbines, coal power equipment, nuclear power equipment, geothermal power equipment, and any other dispatchable baseload energy sources, including electrical infrastructure (including backup power supply) constructed or otherwise used principally to serve a Data Center Project;
(iii) semiconductors and semiconductor materials, such as wafers, dies, and packaged integrated circuits;
(iv) networking equipment, such as switches and routers; and
(v) data storage, such as hardware storage systems, software for data management and protection, and integrated services that work with public cloud providers.
Defines “Covered Component Project,” “Qualifying Project” (based on capital investment, electric load thresholds, national security relevance, or agency designation), “Project Sponsor,” “Superfund Site,” and “Brownfield Site” for purposes of the order.
(c) “Covered Component Project” means infrastructure comprising Covered Components, or a facility with the primary purposes of manufacturing or otherwise producing Covered Components.
(d) “Qualifying Project” means:
(i) a Data Center Project or Covered Component Project for which the Project Sponsor has committed at least $500 million in capital expenditures as determined by the Secretary of Commerce;
(ii) a Data Center Project or Covered Component Project involving an incremental electric load addition of greater than 100 MW;
(iii) a Data Center Project or Covered Component Project that protects national security; or
(iv) a Data Center Project or Covered Component Project that has otherwise been designated by the Secretary of Defense, the Secretary of the Interior, the Secretary of Commerce, or the Secretary of Energy as a “Qualifying Project”.
(e) “Project Sponsor” means the lead sponsor providing financial and other support for a Data Center Project or Covered Component Project, as determined by the Secretary of Defense, the Secretary of the Interior, the Secretary of Commerce, or the Secretary of Energy, as appropriate.
(f) “Superfund Site” means any site where action is being taken pursuant to 42 U.S.C. 9604, 9606, or 9620.
(g) “Brownfield Site” means a site as defined in 42 U.S.C. 9601(39).
Requires the Secretary of Commerce, in consultation with the Director of Office of Science and Technology Policy, to launch an initiative supporting Qualifying Projects with financial aid, directs agencies to identify existing support consistent with national security, and revokes Executive Order 14141.
Sec. 3. Encouraging Qualifying Projects. The Secretary of Commerce, in consultation with the Director of the Office of Science and Technology Policy (OSTP) and other relevant executive departments and agencies (agencies), shall launch an initiative to provide financial support for Qualifying Projects, which could include loans and loan guarantees, grants, tax incentives, and offtake agreements. All relevant agencies shall identify and submit to the Director of OSTP any such relevant existing financial support that can be used to assist Qualifying Projects, consistent with the protection of national security.
Sec. 4. Revocation of Executive Order 14141. Executive Order 14141 of January 14, 2025 (Advancing United States Leadership in Artificial Intelligence Infrastructure), is hereby revoked.
Directs agencies and the Council on Environmental Quality to identify and establish National Environmental Policy Act (NEPA) categorical exclusions for Qualifying Projects and clarifies that certain Federal financial assistance does not constitute a “major Federal action” under NEPA.
Sec. 5. Efficient Environmental Reviews.
(a) Within 10 days of the date of this order, each relevant agency shall identify to the Council on Environmental Quality any categorical exclusions already established or adopted by such agency pursuant to the National Environmental Policy Act (NEPA), reliance on and adoption of which by agencies (pursuant to 42 U.S.C. 4336 and 4336c) could facilitate the construction of Qualifying Projects.
(b) The Council on Environmental Quality shall coordinate with relevant agencies on the establishment of new categorical exclusions to cover actions related to Qualifying Projects that normally do not have a significant effect on the human environment. Agencies shall, for purposes of establishing these categorical exclusions, rely on any sufficient basis to do so as each such agency determines.
(c) Consistent with 42 U.S.C. 4336e(10)(B)(iii), loans, loan guarantees, grants, tax incentives, or other forms of Federal financial assistance for which an agency lacks substantial project-specific control and responsibility over the subsequent use of such financial assistance shall not be considered a “major Federal action” under NEPA. For purposes of this order, Federal financial assistance representing less than 50 percent of total project costs shall be presumed not to constitute substantial Federal control and responsibility.
Allows the Executive Director of the Federal Permitting Improvement Steering Council (FPISC) to designate Qualifying Projects as transparency projects and expedite their publication on Fixing America’s Surface Transportation Act (FAST-41) Permitting Dashboard; further requires expedited transition of transparency projects to FAST-41 "covered projects".
Sec. 6. Efficiency and Transparency Through FAST‑41.
(a) The Executive Director (Executive Director) of the Federal Permitting Improvement Steering Council (FPISC) may, within 30 days of the date that a project is identified to FPISC by a relevant agency, designate a Qualifying Project as a transparency project pursuant to 42 U.S.C. 4370m-2(b)(2)(A)(iii) and section 41003 of the Fixing America’s Surface Transportation Act (Public Law 114-94, 129 Stat. 1312, 1747) (FAST-41). Within 30 days of receiving such agency notification, the Executive Director may publish Qualifying Projects on the Permitting Dashboard established under section 41003(b) of FAST-41, including schedules for expedited review.
(b) In consultation with Project Sponsors, the Executive Director shall expedite the transition of eligible Qualifying Projects from transparency projects to FAST-41 “covered projects” as defined by 42 U.S.C. 4370m(6)(A). To the extent that a Qualifying Project does not meet the criteria set forth in 42 U.S.C. 4370m(6)(A)(i) or (iii), FPISC may consider all other available options to designate the project a covered project under 42 U.S.C. 4370m(6)(A)(iv).
Directs the EPA Administrator to streamline permitting for Qualifying Projects by modifying environmental regulations, identifying eligible Brownfield and Superfund sites, issuing guidance to expedite reviews, and assisting state and private actors in returning such sites to productive use.
Sec. 7. Streamlining of Permitting Review.
(a) The Administrator of the Environmental Protection Agency shall assist in expediting permitting on Federal and non-Federal lands by developing or modifying regulations promulgated under the Clean Air Act (42 U.S.C. 7401 et seq.); the Clean Water Act (33 U.S.C. 1251 et seq.); the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et seq.); the Toxic Substances Control Act (15 U.S.C. 2601 et seq.); and other relevant applicable laws, in each case, that impact the development of Qualifying Projects.
(b) The Administrator of the Environmental Protection Agency shall, consistent with the Environmental Protection Agency’s statutory authorities, expeditiously identify Brownfield Sites and Superfund Sites for use by Qualifying Projects. As part of this effort, within 180 days of the date of this order, the Administrator of the Environmental Protection Agency shall develop guidance to help expedite environmental reviews for qualified reuse and assist State governments and private parties to return such Brownfield Sites and Superfund Sites to productive use as expeditiously as possible.
Directs Secretary of Interior and Commerce to conduct programmatic consultation under the Endangered Species Act for common construction activities of Qualifying Projects and directs the Secretary of the Army to review Clean Water Act and Rivers and Harbors Act nationwide permits to determine whether activity-specific permits are needed, within 180 days.
Sec. 8. Biological and Water Permitting Efficiencies.
(a) Upon identification of sites by the Secretary of the Interior and the Secretary of Energy as described in section 9 of this order, the action agency, as identified through the process described in the Endangered Species Act (16 U.S.C. 1531-1544) (ESA), shall initiate consultation under section 7 of the ESA with the Secretary of the Interior, the Secretary of Commerce, or both with respect to common construction activities for Qualifying Projects that will occur over the next 10 years at a programmatic level. The Secretary of the Interior and the Secretary of Commerce shall utilize programmatic consultation to ensure timely and efficient completion of such consultation.
(b) Within 180 days of the date of this order, the Secretary of the Army, acting through the Assistant Secretary of the Army for Civil Works, shall review the nationwide permits issued under section 404 of the Clean Water Act of 1972 (33 U.S.C. 1344) and section 10 of the Rivers and Harbors Appropriation Act of 1899 (33 U.S.C. 403) to determine whether an activity-specific nationwide permit is needed to facilitate the efficient permitting of activities related to Qualifying Projects.
Directs the Departments of the Interior and Energy to offer authorizations for sites for Qualifying Projects and directs the Secretary of Defense to identify and competitively lease suitable military lands for Covered Component infrastructure and Qualifying Projects, subject to security considerations.
Sec. 9. Federal Lands Availability.
(a) The Department of the Interior and the Department of Energy shall, after consultation with industry and further in consultation with the Department of Commerce as to the Project Sponsors to which relevant authorizations shall be granted, offer appropriate authorizations for sites identified by the Secretary of the Interior or the Secretary of Energy, as applicable and appropriate for the relevant uses, consistent with 42 U.S.C. 2201, 42 U.S.C. 7256, 43 U.S.C. 1701 et seq., and all other applicable law.
(b) The Secretary of Defense shall, pursuant to 10 U.S.C. 2667 or other applicable law and as and when the Secretary of Defense deems it necessary or desirable, identify suitable sites on military installations for Covered Component infrastructure uses and competitively lease available lands for Qualifying Projects to support the Department of Defense’s energy, workforce, and mission needs, subject to security and force protection considerations.
Segment 10
Sec. 10. General Provisions.
(a) Nothing in this order shall be construed to impair or otherwise affect:
(i) the authority granted by law to an executive department or agency, or the head thereof; or
(ii) the functions of the Director of the Office of Management and Budget relating to budgetary, administrative, or legislative proposals.
(b) This order shall be implemented consistent with applicable law and subject to the availability of appropriations.
(c) This order is not intended to, and does not, create any right or benefit, substantive or procedural, enforceable at law or in equity by any party against the United States, its departments, agencies, or entities, its officers, employees, or agents, or any other person.
(d) The costs for publication of this order shall be borne by the Department of Energy.
DONALD J. TRUMP THE WHITE HOUSE, July 23, 2025.